INSP-Final Inspection | 7/20/2020 | 7/27/2020 | 7/27/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Phone #: ###-#### Inspection requested via web by Rose Peterson
|
INSP-Final Inspection | 6/8/2020 | 6/11/2020 | 6/10/2020 | P | CANC |
Troy Cobbley
|
|
|
Inspecting Technician: Ray McQueen Phone #: ###-#### >> Inspection requested via web by Rose Peterson Inspection cancelled from web by: Rose Peterson
|
INSP-Final Inspection | 6/5/2020 | 6/9/2020 | 6/8/2020 | P | CANC |
Troy Cobbley
|
|
|
Inspecting Technician: Ray McQueen Phone #: ###-#### >> Inspection requested via web by Rose Peterson Inspection cancelled from web by: Rose Peterson
|
Plan assigned to (Lee) | 2/11/2020 | | 2/19/2020 | | DONE |
Lee G Meredith
|
|
|
plan mod
|
Plan assigned to (Lee) | 2/19/2020 | | 2/19/2020 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 2/19/2020 | | PASS |
|
|
|
|
1st review completed | | | 2/19/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 2/19/2020 | | 2/19/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/19/2020 | | DONE |
|
|
|
Plan mod passed. Minimum review fee of $65 is due.
|
Permit Ready to Issue | | | 2/19/2020 | | DONE |
|
|
|
DO NOT ISSUE- plan mod approved
|
CHANGE STATUS TO (ISS) | | | 2/19/2020 | | DONE |
|
|
|
plan mod 2 approved
|
Plan Modification Accepted | | | 2/11/2020 | | DONE |
|
|
|
Rose requested workflow to be re opened for plan mod
|
INSP-Final Inspection | 7/17/2019 | 7/23/2019 | 7/23/2019 | A | FAIL |
Troy Cobbley
|
|
|
Lee performed inspection and found that inspeciton could not be performed due to notification in the sleeping rooms not being addressed.
Ray McQueen, inspecting technician Phone #: ###-#### Inspection requested via web by Rose PetersonRay McQueen, inspecting technician Phone #: ###-#### Inspection requested via web by Rose Peterson
|
INSP-Final Inspection | 1/17/2019 | 1/22/2019 | 1/22/2019 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was a walk through to verify device placement. I noted several locations where weather proof backboxes will be required, and notification added. Also in the DIning area a 75cd strobe is overspaced. No small documents are on site but per the notes available online it appears that notification may be required in all of the sleeping rooms. The fire alarm contractor is going to follow up.
Ray McQueen, inspecting technician Phone #: ###-#### Inspection requested via web by Rose Peterson
|
Plan Modification Accepted | | | 1/17/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 1/17/2019 | | 1/17/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/17/2019 | | DONE |
|
|
|
Plan mod review passed, as noted on floor plan. No additional review comments.
|
Permit Ready to Issue | | | 1/17/2019 | | DONE |
|
|
|
Plan mod
|
CHANGE STATUS TO (ISS) | | | 1/17/2019 | | DONE |
|
|
|
|
Miscellaneous action | | | 1/16/2019 | | DONE |
|
|
|
Rose requested the work flow be re-opened for a plan mod.
|
Plan resubmittals received | | | 12/28/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 12/27/2018 | | 12/28/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/28/2018 | | DONE |
|
|
|
Plan review passed with review comments and required changes.
|
Permit Ready to Issue | | | 12/28/2018 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 12/28/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/26/2018 | | DONE |
|
|
|
|
Alarm Plan Check | 12/26/2018 | | 12/26/2018 | | FAIL |
Lee G Meredith
|
|
|
Only room names have been added. The balance of corrections have not been addressed. Resubmittal required.
|
Plan assigned to (Lee) | 12/11/2018 | | 12/12/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 12/12/2018 | | FAIL |
|
|
|
Returned to applicant for noted corrections. Resubmittal required.
|
Application received | | | 12/11/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 11 2018 10:34AM
|