INSP-Final Inspection | 2/26/2019 | 2/27/2019 | 2/27/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Inspection has be around 7or 7:30am Phone #: ###-#### Inspection requested via web by Rafe Barrett
|
INSP-Final Inspection | 2/19/2019 | 2/20/2019 | 2/20/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need the strobe in the restroom removed and as-builts provided.
Inspection needs to be done around 7:30am Phone #: ###-#### Inspection requested via web by Rafe Barrett
|
INSP-Alarm Testing | 2/18/2019 | 2/19/2019 | 2/19/2019 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for tomorrow morning. Phone #: ###-#### Inspection requested via web by Rafe Barrett
|
Application received | | | 12/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 17 2018 11:02AM
|
Plan assigned to (Lee) | 12/17/2018 | | 12/17/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 12/17/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 12/17/2018 | | 12/17/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/17/2018 | | DONE |
|
|
|
Plans approved with review comments.
|
Permit Ready to Issue | | | 12/17/2018 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 12/17/2018 | | DONE |
|
|
|
|