Information based on query as of Sunday, June 23, 2024.
Permit Information
Permit NumberFIR18-00943
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 2906 S GREBE PL
Project NameHARRIS RANCH NORTH LOT 70
Customer Number 
ePlanReviewYes
Description
TFSS TO INSTALL A NEW NFPA 13D FIRE SPRINKLER SYSTEM IN THIS NEW SINGLE FAMILY DWELLING. Plan Mod 2/5/2019 Approved **MAS**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/17/20196/18/20196/18/2019PPASS
DetailsJim Page
Previously noted items have been corrected, final fire sprinkler inspection complete.

Call James before heading out, thanks!
Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Final Inspection6/14/20196/17/20196/17/2019AFAIL
DetailsJim Page
Flow switch test complete, numerous fire sprinklers have gaps next the head when escutcheon is fitted, on-site foreman has notified GC but patches have not been completed. Gaps/painting around heads needs to be complete for final inspection.



Call James before heading out, thanks!
Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Sprinkler Rough-in3/25/20193/26/20193/26/2019PPASS
DetailsJim Page
Rough to cover/tenting inspection for overhead fire sprinkler piping complete, approved for cover.

Tenting at same time as rough/hydro. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro3/25/20193/26/20193/26/2019PPART
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.

Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
Plan assigned to (Stumbaugh)2/4/2019 2/5/2019 PASS
DetailsMark Stumbaugh
Approved
Sprinkler Plan Check2/5/2019 2/5/2019 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  2/5/2019 DONE
DetailsMark Stumbaugh
No Fee
CHANGE STATUS TO (ISS)  2/5/2019 DONE
Plan mod approved, no fees as per Mark
Permit Ready to Issue  2/5/2019 DONE
plan mod approved
CHANGE STATUS TO (ISS)  2/5/2019 DONE
forgot to make plan mod ready
Plan Modification Accepted  2/4/2019 DONE
Adding a double check backflow device. Eplan workflow started.
Issue and Print Permit  12/27/2018 DONE
Plan resubmittals received  12/26/2018 DONE
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)12/26/2018 12/26/2018 DONE
DetailsMark Stumbaugh
Sprinkler Plan Check12/26/2018 12/26/2018 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  12/26/2018 DONE
DetailsMark Stumbaugh
Permit Ready to Issue  12/26/2018 DONE
met
Sprinkler Plan Check12/21/2018 12/21/2018 FAIL
DetailsMark Stumbaugh
Application received  12/17/2018 DONE
Application submitted via PDS Online on Dec 17 2018 2:31PM
Intake Approval  12/17/2018 PASS
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)12/17/2018 12/17/2018 DONE
DetailsMark Stumbaugh