INSP-Final Inspection | 6/17/2019 | 6/18/2019 | 6/18/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final fire sprinkler inspection complete.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 6/14/2019 | 6/17/2019 | 6/17/2019 | A | FAIL |
Jim Page
|
|
|
Flow switch test complete, numerous fire sprinklers have gaps next the head when escutcheon is fitted, on-site foreman has notified GC but patches have not been completed. Gaps/painting around heads needs to be complete for final inspection.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 3/25/2019 | 3/26/2019 | 3/26/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover/tenting inspection for overhead fire sprinkler piping complete, approved for cover.
Tenting at same time as rough/hydro. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 3/25/2019 | 3/26/2019 | 3/26/2019 | P | PART |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Plan assigned to (Stumbaugh) | 2/4/2019 | | 2/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
Approved
|
Sprinkler Plan Check | 2/5/2019 | | 2/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Fee
|
CHANGE STATUS TO (ISS) | | | 2/5/2019 | | DONE |
|
|
|
Plan mod approved, no fees as per Mark
|
Permit Ready to Issue | | | 2/5/2019 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 2/5/2019 | | DONE |
|
|
|
forgot to make plan mod ready
|
Plan Modification Accepted | | | 2/4/2019 | | DONE |
|
|
|
Adding a double check backflow device. Eplan workflow started.
|
Issue and Print Permit | | | 12/27/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/26/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 12/26/2018 | | 12/26/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 12/26/2018 | | 12/26/2018 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/26/2018 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 12/26/2018 | | DONE |
|
|
|
met
|
Sprinkler Plan Check | 12/21/2018 | | 12/21/2018 | | FAIL |
Mark Stumbaugh
|
|
|
|
Application received | | | 12/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 17 2018 2:31PM
|
Intake Approval | | | 12/17/2018 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 12/17/2018 | | 12/17/2018 | | DONE |
Mark Stumbaugh
|
|
|
|