INSP-Final Inspection | 1/30/2019 | 1/31/2019 | 1/31/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 1/28/2019 | | DONE |
|
|
|
As built received with note indicating intellitap II and zone assignments. Approved, subject to inspectors review.
|
INSP-Final Inspection | 1/21/2019 | 1/24/2019 | 1/24/2019 | A | FAIL |
Troy Cobbley
|
|
|
Permit will be ok to final when plan review approved the as-builts.
Please call Nate roughly 20 minutes prior to inspection. Nate can be reached at ###-#### Phone #: ###-#### Inspection requested via web by jason petty
|
Issue and Print Permit | | | 1/2/2019 | | DONE |
|
|
|
|
Application received | | | 12/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 27 2018 8:23AM
|
Plan assigned to (Lee) | 12/27/2018 | | 12/27/2018 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 12/27/2018 | | PASS |
|
|
|
|
Alarm Plan Check | 12/27/2018 | | 12/27/2018 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/27/2018 | | DONE |
|
|
|
Quick permit review passed. No review comments.
|
Permit Ready to Issue | | | 12/27/2018 | | DONE |
|
|
|
met
|