INSP-Final Inspection | 7/26/2019 | 7/26/2019 | 7/26/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Call Anthony before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 7/25/2019 | 7/25/2019 | 7/25/2019 | P | FAIL |
Troy Cobbley
|
|
|
No inspection performed. Fitter did not have means to flow water through an orfice to match the installed sprinkler pendants. No other items looked at. Will need to reschedule.
Call Anthony to coordinate time before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 3/15/2019 | 3/15/2019 | 3/15/2019 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, overhead fire sprinkler piping approved for cover.
Tenting inspection, call Anthony if any issues. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 3/13/2019 | 3/14/2019 | 3/14/2019 | P | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete. Tenting was not installedf at time of inspection, cover is not approved until tenting is insected and passed.
Tenting at same time as rough-hydro. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 3/13/2019 | 3/14/2019 | 3/14/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Rough-hydro, call Anthony before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Plan Modification Accepted | | | 3/11/2019 | | DONE |
|
|
|
Plan mod per attached email, eplan workflow started.
|
Plan assigned to (Stumbaugh) | 3/11/2019 | | 3/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 3/11/2019 | | 3/11/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Fee
|
Permit Ready to Issue | | | 3/11/2019 | | DONE |
|
|
|
plan mod, no fees per Mark
|
(F) Reprint permit | | | 3/11/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/11/2019 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 2/4/2019 | | 2/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Fee
|
Permit Ready to Issue | | | 2/5/2019 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 2/5/2019 | | DONE |
|
|
|
forgot to make plan mod ready
|
Plan Modification Accepted | | | 2/4/2019 | | DONE |
|
|
|
Adding a double check backflow device. Eplan workflow started.
|
Issue and Print Permit | | | 1/8/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/7/2019 | | 1/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 1/7/2019 | | DONE |
|
|
|
met
|
Application received | | | 1/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 4 2019 11:44AM
|
Intake Approval | | | 1/4/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/4/2019 | | 1/4/2019 | | DONE |
Mark Stumbaugh
|
|
|
|