INSP-Final Inspection | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Final Inspection | 2/12/2019 | 2/13/2019 | 2/13/2019 | A | FAIL |
Troy Cobbley
|
|
|
This permit/scope of work is not ready. Wrong permit was called in.
Call Leon Taylor for final inspection on Bodega TI Phone #: ###-#### Inspection requested via web by Sheldon Gray
|
INSP-Sprinkler Rough-in | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overehad fire sprinkler piping above hardlids complete, hardlids approved for cover.
Rough to cover Phone #: ###-#### Inspection requested via web by jeremiah robison
|
Issue and Print Permit | | | 2/5/2019 | | |
|
|
|
|
Intake Approval | | | 1/15/2019 | | FAIL |
Mark Stumbaugh
|
|
|
No stamp area on plan
|
Intake Approval | | | 1/15/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/15/2019 | | 1/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 1/15/2019 | | 1/15/2019 | | PASS |
Mark Stumbaugh
|
|
|
As Noted
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/15/2019 | | PASS |
Mark Stumbaugh
|
|
|
Approved as noted on plan
|
Permit Ready to Issue | | | 1/15/2019 | | DONE |
|
|
|
met
|
Application received | | | 1/10/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 10 2019 11:10AM
|