INSP-Final Inspection | 6/5/2019 | 6/6/2019 | 6/6/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Gabe Garduno is the contact. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/28/2019 | 5/29/2019 | 5/29/2019 | A | PASS |
Troy Cobbley
|
|
|
Hydro test witnessed with no visible loss on the guage.
Gabe Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test failed due to visible loss on the guage.
|
INSP-Supply line flush | 5/21/2019 | 5/22/2019 | 5/22/2019 | A | PASS |
Troy Cobbley
|
|
|
The undergrond supply line flush was witnessed.
|
INSP-Sprinkler Rough-in | 2/7/2019 | 2/7/2019 | 2/7/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for undergorund supply complete, approved for cover.
Call Jim Page to verify he witness pipe installation back in 2018. The Shilo contact is Brian Collins. Thanks for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Intake Approval | | | 1/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/25/2019 | | 1/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 1/25/2019 | | 1/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 1/25/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/25/2019 | | DONE |
|
|
|
|
Application received | | | 1/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 19 2019 4:55PM
|