INSP-Final Inspection | 4/3/2019 | 4/4/2019 | 4/4/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overehad fire sprinkler piping in area of work complete, area of work approved for cover.
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/6/2019 | 3/6/2019 | 3/6/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids in area of work complete, hardlids approved for cover.
Todd Ketterling is the contact. Thank you for your work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Sprinkler Plan Check | 1/30/2019 | | 2/11/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/11/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 2/11/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/30/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/30/2019 | | 1/30/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 1/25/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Job needs to be submitted as a 603 permit. New TI's will require hydraulic calculations, eq bracing calcs, etc as required for a 603 permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 1/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 21 2019 9:41AM
|