INSP-Final Inspection | 5/6/2019 | 5/7/2019 | 5/7/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Todd Ketterling is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/19/2019 | 4/19/2019 | 4/19/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Todd Ketterling is the contact for this RTC inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Issue and Print Permit | | | 2/20/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/19/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/19/2019 | | 2/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/19/2019 | | 2/19/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/19/2019 | | DONE |
|
|
|
met
|
Sprinkler Plan Check | 1/30/2019 | | 2/12/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Waiting for building permit to be approved, and pickup.
Resubmit after approval of BLD19-00210
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 1/30/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/30/2019 | | 1/30/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 1/25/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Job needs to be submitted as a 603 permit. New TI's will require hydraulic calculations, eq bracing calcs, etc as required for a 603 permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 1/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 21 2019 2:58PM
|