INSP-Final Inspection | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Nick Phone #: ###-####
|
INSP-Final Inspection | 8/21/2019 | 8/22/2019 | 8/22/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need insulation and cover inspection for the piping in the storage closets.
Nick Phone #: ###-#### (change inspection to this afternoon, 8-22, per kristin dolan)
|
INSP-Final Inspection | 8/12/2019 | 8/12/2019 | 8/12/2019 | P | FAIL |
Jim Page
|
|
|
Provide freeze protection for fire sprinkler piping in storage closets. Storage closets have exposed CPVC, exposed CPVC is not allowed per manufacture specs. Provide signage for FDC bell as required.
Kristin Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/6/2019 | 5/6/2019 | 5/6/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered. The wet pipe in the exterior closets will need addressed as per previous conversations.
###-#### Nick
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test was witnessed with no visible loss at the guage. Todd Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/30/2019 | | DONE |
|
|
|
PLAN MOD
|
Plan resubmittals received | | | 4/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/29/2019 | | 4/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/29/2019 | | 4/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
Resubmittal Fee $110.25
|
Permit Ready to Issue | | | 4/29/2019 | | DONE |
|
|
|
Plan mod approved. fees due for two plan mods before changing permit back to issued.
|
INSP-Supply line flush | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground flush witnessed
Call ahead // Nick Phone #: ###-####
|
Plan assigned to (Stumbaugh) | 4/26/2019 | | 4/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/26/2019 | | 4/26/2019 | | FAIL |
Mark Stumbaugh
|
|
|
No letter explaining what plan mod is for.
|
Plan Modification Accepted | | | 4/25/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/24/2019 | | 4/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 4/24/2019 | | |
|
|
|
plan mod DO NOT REISSUE
|
Meeting | | | 4/24/2019 | | DONE |
|
|
|
Plan mod per Kristin. Deleted previous plan mod docs. Fees were not paid.
|
Plan Modification Accepted | | | 4/19/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/19/2019 | | 4/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/19/2019 | | 4/19/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
Resubmittal fee $110.25
|
Permit Ready to Issue | | | 4/19/2019 | | DONE |
|
|
|
plan mod approved
DO NOT REISSUE
|
Sprinkler Plan Check | 4/9/2019 | | 4/10/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 4/9/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/9/2019 | | 4/9/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/3/2019 | | 4/4/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 4/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/3/2019 | | 4/3/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/28/2019 | | 3/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 3/28/2019 | | 3/28/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/27/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/27/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/25/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/15/2019 | | 3/20/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/20/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/15/2019 | | DONE |
|
|
|
per Kristin started plan mod-changing mvoing risers-adding sheet # FP1
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/1/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 2/1/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/28/2019 | | 2/1/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Miscellaneous action | | | 1/29/2019 | | DONE |
|
|
|
permit was submitted with the wrong address 9357 W Cory-changed address per Mark Stumbaugh to 9333 W Cory Ln
|
Intake Approval | | | 1/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/28/2019 | | 1/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 1/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 24 2019 8:55AM
|