INSP-Final Inspection | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Nick Phone #: ###-####
|
INSP-Final Inspection | 8/21/2019 | 8/22/2019 | 8/22/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need insulation and cover inspection for the piping in the storage closets.
Nick Phone #: ###-#### (change inspection to this afternoon, 8-22, per kristin dolan)
|
INSP-Final Inspection | 8/12/2019 | 8/12/2019 | 8/12/2019 | P | FAIL |
Jim Page
|
|
|
Last inspection request was on 21MAY2019 for cover, notes indicate cover was not approved due too no tenting being installed, cover material has been installed and according to the last entry, cover was not approved.
Kristin Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2019 | 5/21/2019 | 5/21/2019 | P | FAIL |
Troy Cobbley
|
|
|
A tenting inspection was requested but no tenting has been installed.
Nick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/6/2019 | 5/6/2019 | 5/6/2019 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed but piping can not be covered until a tenting inspection has passed.
Nick Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2019 | 4/30/2019 | 4/30/2019 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test witnessed with no visible loss on the guage. Todd Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/30/2019 | | DONE |
|
|
|
PLAN MOD
|
Permit Ready to Issue | | | 4/29/2019 | | DONE |
|
|
|
plan mod approved. fees due- DO NOT RE ISSUE
|
Plan resubmittals received | | | 4/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/29/2019 | | 4/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/29/2019 | | 4/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
Resubmittal Fee #110.25
|
INSP-Supply line flush | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Troy Cobbley
|
|
|
Underground flush witnessed
Nick Phone #: ###-####
|
Plan assigned to (Stumbaugh) | 4/26/2019 | | 4/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/26/2019 | | 4/26/2019 | | FAIL |
Mark Stumbaugh
|
|
|
No letter explaining what plan mod is for
|
Plan Modification Accepted | | | 4/25/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Fees Due Hold | 4/19/2019 | | 4/25/2019 | | DONE |
Brittany Hill
|
|
|
|
Plan Modification Accepted | | | 4/24/2019 | | DONE |
|
|
|
Plan mod DO NOT ISSUE per Kristin Nolan
|
Meeting | | | 4/24/2019 | | DONE |
|
|
|
plan mod per Kristin. FINAL FEES HAVE NOT BEEN PAID
|
Sprinkler Plan Check | 4/9/2019 | | 4/10/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/10/2019 | | DONE |
Mark Stumbaugh
|
|
|
Fee $110.25
|
Issue and Print Permit | | | 4/10/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/9/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/9/2019 | | 4/9/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/3/2019 | | 4/8/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 4/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/3/2019 | | 4/3/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/28/2019 | | 3/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 3/28/2019 | | 3/28/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/27/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/27/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/25/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/15/2019 | | 3/20/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/20/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan Modification Accepted | | | 3/15/2019 | | DONE |
|
|
|
per Kristin started plan mod-changing mvoing risers-adding sheet # FP1
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/1/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 2/1/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/28/2019 | | 2/1/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Miscellaneous action | | | 1/29/2019 | | DONE |
|
|
|
permit was submitted with the wrong address 9357 W Cory-changed address per Mark Stumbaugh to 9345 W Cory Ln
|
Intake Approval | | | 1/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/28/2019 | | 1/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 1/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 24 2019 9:02AM
|