INSP-Final Inspection | 5/15/2019 | 5/16/2019 | 5/16/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
sprinkler final // Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with red ink areas approved for cover.
Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/9/2019 | 5/10/2019 | 5/10/2019 | P | CANC |
Troy Cobbley
|
|
|
Not all work was complete. To be rescheduled.Tom Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/1/2019 | 5/2/2019 | 5/2/2019 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas on the second floor where piping is ok for cover. Tom and I went over sprinkler coverage in/below the clouds.
Tom Phone #: ###-####
|
Issue and Print Permit | | | 2/21/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/14/2019 | | 2/20/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/20/2019 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 2/14/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 2/14/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/14/2019 | | 2/14/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 1/31/2019 | | 2/7/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Corrections Needed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 1/31/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 31 2019 11:36AM
|
Intake Approval | | | 1/31/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/31/2019 | | 1/31/2019 | | DONE |
Mark Stumbaugh
|
|
|
|