INSP-Final Inspection | 6/12/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Plan assigned to (Lee) | 6/7/2019 | | 6/11/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 6/11/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 6/11/2019 | | 6/11/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/11/2019 | | DONE |
|
|
|
As Built - No Fee
|
Permit Ready to Issue | | | 6/11/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/11/2019 | | |
|
|
|
|
Plan resubmittals received | | | 6/7/2019 | | DONE |
|
|
|
As built open requested by Morgan- candla change and upstairs device
|
INSP-Final Inspection | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | FAIL |
Troy Cobbley
|
|
|
Plan mod needed for changing the hallway strobes to 30cd, need to show Mezzanine and Mechanical Room notification devices, need to test Gym duct smoke detectors and change two devices to weather proof. Need to witness notification testing.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Plan assigned to (Lee) | 5/9/2019 | | 6/4/2019 | | DONE |
Lee G Meredith
|
|
|
plan mod
Uploaded 6-4-19.
|
1st review completed | | | 6/4/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 6/4/2019 | | 6/4/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/4/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/4/2019 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 6/4/2019 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 5/9/2019 | | DONE |
|
|
|
Per Morgan from Protex, start a plan mod workflow
|
INSP-Final Inspection | 3/21/2019 | 3/22/2019 | 3/22/2019 | P | PART |
Troy Cobbley
|
|
|
Phase 1 fire alarm complete. See comments by Lee for items needing correcting from the Phase 1 inspection prior to a final fire alarm permit sign off.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Miscellaneous action | | | 3/22/2019 | | DONE |
|
|
|
As built drawings received and passed.
|
(F) Reprint permit | | | 3/22/2019 | | DONE |
|
|
|
|
Miscellaneous action | | | 3/22/2019 | | DONE |
|
|
|
During the phase 1 inspection, the following item was found to be needing correction. Kitchen strobe exceeded allowed distance for the candela provided. Dirk increased the cndela from 30 to 75. Riser, calcs. and floor plan need to show this change.
|
INSP-Final Inspection | 3/20/2019 | 3/21/2019 | 3/21/2019 | P | FAIL |
Troy Cobbley
|
|
|
Not all of the plan package on site, drawings (facp, amp not same as drawings) no dialer shown, smoke over facp too low. No testing performed.
Partial Final for cafeteria and commons. Dirk is Contact. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Plan Modification Accepted | | | 3/20/2019 | | DONE |
|
|
|
Per Morgan from Protex who requested new workflow
|
Plan assigned to (Lee) | 3/20/2019 | | 3/20/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/20/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 3/20/2019 | | 3/20/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/20/2019 | | DONE |
|
|
|
As built drawings approved. No additional review comments.
|
Permit Ready to Issue | | | 3/20/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/20/2019 | | DONE |
|
|
|
PLAN MOD NO FEES AS BUILT
|
Miscellaneous action | | | 3/12/2019 | | DONE |
|
|
|
Rob called to say the school district decided to remove interface between buildings but the seperate GSM will be kept. I told him to provide as builts when tiime for sign off.
|
Miscellaneous action | | | 2/28/2019 | | DONE |
|
|
|
Received product data for a GSM communicator and updated riser drawing.
|
Issue and Print Permit | | | 2/6/2019 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 2/1/2019 | | 2/5/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/5/2019 | | PASS |
|
|
|
Passed as noted.
|
Alarm Plan Check | 2/5/2019 | | 2/5/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/5/2019 | | DONE |
|
|
|
Review passed with comments and drawing notes.
|
Permit Ready to Issue | | | 2/5/2019 | | DONE |
|
|
|
met
|
Application received | | | 2/1/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 1 2019 10:51AM
|