INSP-Alarm Testing | 2/19/2019 | 2/19/2019 | 2/19/2019 | P | CANC |
Jim Page
|
|
|
Please call 1/2 hour ahead Phone #: ###-#### Inspection requested via web by Rafe Barrett
|
INSP-Final Inspection | 2/19/2019 | 2/19/2019 | 2/19/2019 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection for area of work complete.
|
CHANGE STATUS TO (ISS) | | | 2/19/2019 | | DONE |
|
|
|
Plan Mod
|
Miscellaneous action | | | 2/15/2019 | | DONE |
|
|
|
Work flow opened to upload design corrections
|
Plan Modification Accepted | | | 2/15/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 2/15/2019 | | 2/15/2019 | | PASS |
Lee G Meredith
|
|
|
Corrections passed.
|
PLANS TAKEN FRONT DESK ALARM | | | 2/15/2019 | | DONE |
|
|
|
Corrections passed. No additional review comments.
|
Permit Ready to Issue | | | 2/15/2019 | | DONE |
|
|
|
plan mods approved
|
INSP-Final Inspection | 2/13/2019 | 2/13/2019 | 2/13/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need plan mods for deleting the ceiling mounted horn/strobe in the now Office and the device in the Restroom needs changed out to match the new devices so that the all function together
Please call 1/2 hour ahead of time Phone #: ###-#### Inspection requested via web by Rafe Barrett
|
Application received | | | 2/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 4 2019 10:49AM
|
1st review completed | | | 2/4/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 2/4/2019 | | 2/4/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/4/2019 | | DONE |
|
|
|
Passed with review comments.
|
Permit Ready to Issue | | | 2/4/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 2/4/2019 | | DONE |
|
|
|
|