INSP-Final Inspection | 6/3/2019 | 6/4/2019 | 6/4/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 5/28/2019 | 5/29/2019 | 5/29/2019 | A | FAIL |
Troy Cobbley
|
|
|
Permit can be finaled when the test documents have been provided as discussed. Also the underground permit needs to be scheduled for a final inspection.
Gabe Phone #: ###-####
|
INSP-Final Inspection | 5/24/2019 | 5/28/2019 | 5/28/2019 | A | CANC |
Troy Cobbley
|
|
|
not ready per Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2019 | 5/22/2019 | 5/22/2019 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro tested witnessed with no visible loss on the guage.
|
Fees Due Hold | 5/16/2019 | | 5/17/2019 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 5/14/2019 | 5/15/2019 | 5/15/2019 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro tests failed again do to visible loss on the guages. A re-inspection fee has been applied.
|
INSP-Sprinkler Rough-in/Hydro | 5/13/2019 | 5/14/2019 | 5/14/2019 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro tests failed due to visible loss on both guages. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro failed due to visible loss of pressure on the guages.
Gabe Garduno is the contact. This is for a hydro only inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
CHANGE STATUS TO (ISS) | | | 5/10/2019 | | DONE |
|
|
|
plan mod
|
Plan assigned to (Stumbaugh) | 5/8/2019 | | 5/9/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 5/9/2019 | | 5/9/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2019 | | DONE |
Mark Stumbaugh
|
|
|
Plan Mod Fee $150.00
|
Permit Ready to Issue | | | 5/9/2019 | | DONE |
|
|
|
plan mod
|
Plan Modification Accepted | | | 5/8/2019 | | DONE |
|
|
|
changing the supply line in the crawl space from CPVC to Sch 40 Black Steel
|
INSP-Sprinkler Rough-in | 3/7/2019 | 3/8/2019 | 3/8/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Tenting passed. Piping can be covered. Sprinkler protection for the second floor outside storage rooms may need to be modified. As-builts are needed showing the new sidewall coverage under the front entry gables.Rirers are not built yet.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/5/2019 | 3/5/2019 | 3/5/2019 | P | FAIL |
Troy Cobbley
|
|
|
Project is not ready yet for a complete rough-in inspection due to many missing heads in closets, balcony/storage closets, breezwway coverage, missing insulation for tenting. Also I noted that the breezeway has a soffit that may obstruct the sidewall sprinkler coverage.
Gabe Garduno is the contact. Thank you for all the help you give! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan resubmittals received | | | 2/15/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/15/2019 | | 2/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/15/2019 | | 2/15/2019 | | PASS |
Mark Stumbaugh
|
|
|
Approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/15/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 2/15/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/13/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 2/13/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/13/2019 | | 2/13/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/13/2019 | | 2/13/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Corrections needed see noted plan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 2/12/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 12 2019 5:51AM
|
Intake Approval | | | 2/12/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/12/2019 | | 2/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/12/2019 | | 2/12/2019 | | FAIL |
Mark Stumbaugh
|
|
|
corrections needed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|