INSP-Final Inspection | 4/22/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection for the area of work associated with this permit is complete, levels 7 and 8 have been inspected which now finals this permit scope of work.
Josh Phone #: ###-####
|
INSP-Final Inspection | 4/4/2019 | 4/4/2019 | 4/4/2019 | P | PART |
Jim Page
|
|
|
Final fire alarm inspection for levels 4, 5 and 6 complete. Remaining work to be completed at a later date.
|
INSP-Alarm Testing | 4/2/2019 | 4/4/2019 | 4/4/2019 | P | DONE |
Jim Page
|
|
|
Fire alarm testing complete.
Josh-partial on floors 4, 5 & 6 Phone #: ###-####
|
Issue and Print Permit | | | 2/28/2019 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 2/25/2019 | | 2/25/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/25/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 2/25/2019 | | 2/25/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/25/2019 | | DONE |
|
|
|
Review passed with comments.
|
Permit Ready to Issue | | | 2/25/2019 | | DONE |
|
|
|
|
Application received | | | 2/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 24 2019 6:39PM
|