INSP-Final Inspection | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
contact Lonnie to cordinate final inpsection Phone #: ###-#### Inspection requested via web by Christophe Wilson
|
INSP-Sprinkler Rough-in | 10/15/2019 | 10/15/2019 | 10/15/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlid and suspeneded ceiling, west coridor complete, area inspected approved for cover.
Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
INSP-Sprinkler Rough-in | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
INSP-Sprinkler Rough-in | 8/19/2019 | 8/20/2019 | 8/20/2019 | P | PART |
Jim Page
|
|
|
Rough in inspection for dry system addition on top level of parking structure complete.
Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
INSP-Sprinkler Rough-in | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping in area of work complete, notated the city approved drawings with red ink areas approved for cover.
Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
INSP-Sprinkler Rough-in | 7/26/2019 | 7/26/2019 | 7/26/2019 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspectionfor overhead fire sprinkler piping in area of work complete, notated the city approved drawings with red ink areas approved for cover.
Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
INSP-Sprinkler Rough-in | 6/11/2019 | 6/12/2019 | 6/12/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for sprinkler piping above hardlids in locker rooms complete, approved for cover.
Lonnie Phone #: ###-#### Inspection requested via web by Lonnie Greenfield
|
Issue and Print Permit | | | 3/13/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/12/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/12/2019 | | 3/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 3/12/2019 | | 3/12/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 3/12/2019 | | DONE |
|
|
|
met
|
Sprinkler Plan Check | 3/5/2019 | | 3/8/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/8/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 3/5/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 5 2019 12:10PM
|
Intake Approval | | | 3/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/5/2019 | | 3/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|