INSP-Final Inspection | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/12/2019 | 6/13/2019 | 6/13/2019 | A | PASS |
Troy Cobbley
|
|
|
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed for remaining piping. Piping is ok for cover.
|
INSP-Sprinkler Rough-in | 4/17/2019 | 4/18/2019 | 4/18/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids notated on city approved drawing complete, area notated with red ink approved for cover.
Todd Ketterling is the contact. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Intake Approval | | | 3/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/25/2019 | | 3/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 3/25/2019 | | 3/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 3/25/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 3/25/2019 | | DONE |
|
|
|
|
Application received | | | 3/14/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 14 2019 9:10AM
|
Intake Approval | | | 3/14/2019 | | FAIL |
Mark Stumbaugh
|
|
|
BLD permit still inder review. Resubmit after BLD19-00411 is issued.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2019 | | DONE |
Mark Stumbaugh
|
|
|
|