INSP-Final Inspection | 5/17/2019 | 5/17/2019 | 5/17/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Call Troy with time frame.
Thank you and a have a great day. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in | 4/17/2019 | 4/17/2019 | 4/17/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in scope of work complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/17/2019 | 4/17/2019 | 4/17/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping associated with this system witnessed, no pressure loss observed.
Please Cordinate inspection with Troy Nelson Thanks Phone #: ###-#### Inspection requested via web by Christophe Wilson
|
Plan resubmittals received | | | 4/16/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/16/2019 | | 4/16/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/16/2019 | | 4/16/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/16/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/16/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 4/16/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/12/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/3/2019 | | 4/9/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 4/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/3/2019 | | 4/3/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 3/22/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Building permit under review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/22/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 3/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 21 2019 3:20PM
|