INSP-Final Inspection | 7/2/2019 | 7/3/2019 | 7/3/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Plans are in Marks office Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Troy Cobbley
|
|
|
5 heads in hard lid ceiling are ok for cover. Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 4/15/2019 | 4/15/2019 | 4/15/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for drops supplying flex heads complete, approved for cover.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
Sprinkler Plan Check | 4/3/2019 | | 4/8/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Returned at contractor's request
|
Plan resubmittals received | | | 4/8/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/8/2019 | | 4/8/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/8/2019 | | 4/8/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/8/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 4/8/2019 | | DONE |
|
|
|
|
Intake Approval | | | 4/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/3/2019 | | 4/3/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 3/26/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Awaiting BLD19-00513 to be issued
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 3/25/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 25 2019 2:42PM
|