INSP-Final Inspection | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Rick Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Sprinkler Rough-in | 5/3/2019 | 5/3/2019 | 5/3/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
Jon O Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
Plan assigned to (Stumbaugh) | 4/26/2019 | | 4/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/29/2019 | | 4/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/29/2019 | | DONE |
|
|
|
PLAN MOD
|
CHANGE STATUS TO (ISS) | | | 4/29/2019 | | DONE |
|
|
|
NO FEES PER MARK STUMBAUGH
|
INSP-Sprinkler Rough-in/Hydro | 4/26/2019 | 4/26/2019 | 4/26/2019 | P | FAIL |
Troy Cobbley
|
|
|
Per the city approved plans the front area is considered an "M" occupancy and will need the pendant heads spaced for ordinary hazard not light hazard. Adam Phone #: ###-####
|
Plan Modification Accepted | | | 4/26/2019 | | DONE |
|
|
|
Per Nathan Stenquist. Changing from standard spray sprinklers to extended coverage sprinklers and using flesible drops.
|
Application received | | | 3/27/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 27 2019 12:22PM
|
Intake Approval | | | 3/27/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 3/27/2019 | | 3/27/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 3/27/2019 | | 3/27/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/27/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 3/27/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/27/2019 | | DONE |
|
|
|
|