INSP-Final Inspection | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for core and shell complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2019 | 7/29/2019 | 7/29/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 7/8/2019 | 7/9/2019 | 7/9/2019 | A | PASS |
Jim Page
|
|
|
Rough in inspection for interior sprinkler piping complete, no cover for interior piping, scope of work is for core and shell protection only. Rough to cover inspection for overhead fire sprinkler piping in exterior canopies complete, exterior canopies approved for cover.
Adam Phone #: ###-####
|
INSP-Conference | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | DONE |
Jim Page
|
|
|
Gas meter is set in the wrong location, city approved drawings show gas meter by north door, currently meter is set under PIV for fire sprinklers, needs to be relocated to give the required 36 inch clearance around PIV.
|
Plan Modification Accepted | | | 6/24/2019 | | DONE |
|
|
|
Plan mod #2 requested by Mathew Lewis, moved HVAC units, branchline layout re-done. New calc due to the chage.
|
Plan assigned to (Stumbaugh) | 6/24/2019 | | 6/24/2019 | | DONE |
Mark Stumbaugh
|
|
|
plan mod cancelled
|
CHANGE STATUS TO (ISS) | | | 6/24/2019 | | DONE |
|
|
|
wrong number given for plan mod per Mark Stumbaugh
|
INSP-Supply line flush | 6/3/2019 | 6/5/2019 | 6/5/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
AT 9:00 WITH Suez. Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Supply line flush | 6/3/2019 | 6/5/2019 | 6/3/2019 | A | CANC |
Jim Page
|
|
|
Please Contact Troy Nelson Phone #: ###-#### >> Inspection requested via web by Daniel Buccino Inspection cancelled from web by: Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2019 | 5/20/2019 | 5/20/2019 | P | DONE |
Jim Page
|
|
|
Underground hydrostatic test witnessed, no pressure loss observed.
UNDERGROUND HYDRO Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 5/3/2019 | 5/3/2019 | 5/3/2019 | P | PASS |
Troy Cobbley
|
|
|
*** OK to cover underground. No hydro or flush at this time.*MAS***
underground rough. Will call when ready. Phone #: ###-#### >> Inspection requested via web by Matthew Lewis
|
Issue and Print Permit | | | 5/2/2019 | | DONE |
|
|
|
accidently issued it again, it was 1st issued on 5/2/19
|
Plan resubmittals received | | | 5/1/2019 | | DONE |
|
|
|
per Matt Lewis re-opened, plan mod to change 6' underground to 4" and backflow from 2.5 to 3
|
Plan assigned to (Stumbaugh) | 5/1/2019 | | 5/1/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 5/1/2019 | | 5/1/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2019 | | DONE |
Mark Stumbaugh
|
|
|
Plan Mod Fee $150.00
|
Permit Ready to Issue | | | 5/1/2019 | | DONE |
|
|
|
PLAN MOD
|
Issue and Print Permit | | | 4/11/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/3/2019 | | 4/9/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/9/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/9/2019 | | DONE |
|
|
|
|
Application received | | | 4/3/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 3 2019 9:33AM
|
Intake Approval | | | 4/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/3/2019 | | 4/3/2019 | | DONE |
Mark Stumbaugh
|
|
|
|