INSP-Final Inspection | 5/17/2019 | 5/20/2019 | 5/20/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Phone #: ###-#### Inspection requested via web by Mick Woodburn
|
INSP-Sprinkler Rough-in | 4/9/2019 | 4/10/2019 | 4/10/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed.
Contact Chris Felty Phone #: ###-#### Inspection requested via web by Matt Barnard
|
Issue and Print Permit | | | 4/4/2019 | | DONE |
|
|
|
|
Application received | | | 4/3/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 3 2019 11:50AM
|
Intake Approval | | | 4/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/3/2019 | | 4/3/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/3/2019 | | 4/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/3/2019 | | DONE |
|
|
|
met
|