INSP-Final Inspection | 6/12/2019 | 6/13/2019 | 6/13/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Please call Clarence before heading to job site. Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2019 | 5/3/2019 | 5/3/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
Please call clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 5/2/2019 | 5/3/2019 | 5/3/2019 | P | CANC |
Troy Cobbley
|
|
|
Please call clarence Phone #: ###-#### >> Inspection requested via web by Jessia Maxwell Inspection cancelled from web by: Jessia Maxwell
|
Intake Approval | | | 4/26/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/26/2019 | | 4/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/26/2019 | | 4/26/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/26/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/26/2019 | | DONE |
|
|
|
|
Intake Approval | | | 4/17/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Waiting for Building permit to be issued
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 4/10/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 10 2019 10:44AM
|