INSP-Final Inspection | 11/27/2019 | 12/3/2019 | 12/3/2019 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection is complete.
6am per Joe Bruce // Damien Phone #: ###-####
|
Fees Due Hold | 11/27/2019 | | 11/27/2019 | | DONE |
|
|
|
|
INSP-Final Inspection | 11/26/2019 | 11/26/2019 | 11/26/2019 | A | FAIL |
Jim Page
|
|
|
Fire alarm has audio issues with the three temporal, a re-inspection will be required after audio issue is resolved.
###-#### - Damien
|
CHANGE STATUS TO (ISS) | | | 11/21/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/19/2019 | | DONE |
|
|
|
3rd as built per Kristian -location moves
|
Plan assigned to (Lee) | 11/19/2019 | | 11/19/2019 | | DONE |
Lee G Meredith
|
|
|
4th as built per Kristian -location moves
|
1st review completed | | | 11/19/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 11/19/2019 | | 11/19/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/19/2019 | | DONE |
|
|
|
Plan mod passed. $65.00 one hour minimum review fee due.
|
Permit Ready to Issue | | | 11/19/2019 | | DONE |
|
|
|
Plan mod approved
|
INSP-Final Inspection | 11/13/2019 | 11/14/2019 | 11/14/2019 | A | FAIL |
Jim Page
|
|
|
City approved drawings have been notated areas that need to be corrected. Relocate dcevices that are overspaced or adjust candella setting. Provide weather proof devices in restrooms that have showers. Add notication in multi-person offices as dicussed.
5am
|
Fees Due Hold | 11/13/2019 | | 11/13/2019 | | DONE |
|
|
|
|
INSP-Final Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 | P | PART |
Jim Page
|
|
|
Fire alarm inspection for surgical suite, southwest side of building complete to include corridors outside of surgical suite. Remaining areas to be inspected at a later date.
Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
Plan resubmittals received | | | 11/4/2019 | | DONE |
|
|
|
Lauren called to have the workflow opened for as builts #2
|
Plan assigned to (Lee) | 11/4/2019 | | 11/4/2019 | | DONE |
Lee G Meredith
|
|
|
as built
|
1st review completed | | | 11/4/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 11/4/2019 | | 11/4/2019 | | PASS |
Lee G Meredith
|
|
|
|
Plan Modification Accepted | | | 11/4/2019 | | DONE |
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/4/2019 | | DONE |
|
|
|
Plan mod passed. Minimum review fee of $65 is due.
|
Permit Ready to Issue | | | 11/4/2019 | | DONE |
|
|
|
DO NOT ISSUE -Plan mod approved
|
CHANGE STATUS TO (ISS) | | | 11/4/2019 | | DONE |
|
|
|
PLAN MOD
|
Fees Due Hold | 10/25/2019 | | 10/25/2019 | | DONE |
|
|
|
|
INSP-Final Inspection | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | FAIL |
Jim Page
|
|
|
Relocate smoke detectors that are to close to HVAC registers. Provide weather proof A/V devides in prep area behind surgical suites. Verify if door hold magnets are going to stay in place, if door holds stay then smoke detectors will be required for door release.
Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
INSP-Final Inspection | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | FAIL |
Jim Page
|
|
|
Occupancy is a B occupancy, provide notification in post op and pre op rooms. Relocate notification in areas as discussed. No devices tested.
Call ahead to Damien @ ###-#### Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
Plan assigned to (Lee) | 10/21/2019 | | 10/22/2019 | | DONE |
Lee G Meredith
|
|
|
as built
|
Intake Approval | | | 10/22/2019 | | PASS |
|
|
|
|
1st review completed | | | 10/22/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 10/22/2019 | | 10/22/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/22/2019 | | DONE |
|
|
|
As built - No fee
|
Permit Ready to Issue | | | 10/22/2019 | | DONE |
|
|
|
as built approved
|
CHANGE STATUS TO (ISS) | | | 10/22/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/21/2019 | | DONE |
|
|
|
start as built workflow per Kristin at Johnson Controls
|
Telephone call | | | 9/25/2019 | | DONE |
|
|
|
Received a call from the architect at Hummel. He said that he had discussed the requirements of interfacing the fire alarm system to the elevator in question with Gary Barnes. Gary informed him that due to the age and length of travel, interface will not be required.
|
Meeting | | | 9/19/2019 | | DONE |
|
|
|
Met with GC regarding elevator recall. He indicated that one of the existing elevators was not capable of recall and wanted direction on how to accomplish shunt. I informed him that shunt cannot be installed if elevator is not capable of full recall. Told him to contact Gary Barnes from the state elevator inspectors office for direction.
|
Plan resubmittals received | | | 5/2/2019 | | DONE |
|
|
|
|
1st review completed | | | 5/2/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 5/2/2019 | | 5/2/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/2/2019 | | DONE |
|
|
|
Passed with requirements noted on drawings.
|
Permit Ready to Issue | | | 5/2/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 5/2/2019 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 4/23/2019 | | 4/24/2019 | | DONE |
Lee G Meredith
|
|
|
|
Plan resubmittals received | | | 4/24/2019 | | DONE |
|
|
|
|
1st review completed | | | 4/24/2019 | | FAIL |
|
|
|
All plans resubmitted with incorrect file name. Returned again to applicant for correction. New files were deleted and applicant was emailed correction requirements.
|
Application received | | | 4/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 16 2019 11:56AM
|