INSP-Final Inspection | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
|
INSP-Sprinkler Rough-in | 5/10/2019 | 5/13/2019 | 5/13/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in scope of work complete, approved for cover.
Tom Phone #: ###-####
|
Application received | | | 4/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 17 2019 7:19AM
|
Intake Approval | | | 4/17/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/17/2019 | | 4/17/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/17/2019 | | 4/17/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/17/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 4/17/2019 | | DONE |
|
|
|
|