INSP-Final Inspection | 6/25/2020 | 6/25/2020 | 6/25/2020 | P | PASS |
Troy Cobbley
|
|
|
permit finaled.
Call Jeff if there are questions. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Final Inspection | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | PART |
Troy Cobbley
|
|
|
Fire sprinkler work in the new restrooms is complete.
|
INSP-Sprinkler Rough-in | 8/26/2019 | 8/26/2019 | 8/26/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed for the two rooms. Combustible concealed spaces are full of insulation. Piping can be covered.
Kerry Turner Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
CHANGE STATUS TO (ISS) | | | 8/26/2019 | | DONE |
|
|
|
plan mod fee paid
|
Plan Modification Accepted | | | 8/7/2019 | | DONE |
|
|
|
plan mod started in e plan per Brodie Stenquist-assigned to MAS
|
Plan assigned to (Stumbaugh) | 8/7/2019 | | 8/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 8/7/2019 | | 8/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
Plan Mod to add 1 head in new restroom.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
Plan Mod Fee $150.00
|
Permit Ready to Issue | | | 8/7/2019 | | DONE |
|
|
|
plan mod-do not re issue
|
Intake Approval | | | 4/19/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/19/2019 | | 4/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/19/2019 | | 4/19/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/19/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 4/19/2019 | | DONE |
|
|
|
|
Application received | | | 4/18/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 18 2019 3:18PM
|