INSP-Final Inspection | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Please call Adam with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in/Hydro | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test witnessed at city pressure, no pressure loss observed.
Please call Adam with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Supply line flush | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Troy will coordinate with Suez. Troy Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Supply line flush | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | CANC |
Troy Cobbley
|
|
|
Could not perform inspection due to time constraints. Please call troy with time frame. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in | 8/14/2019 | 8/14/2019 | 8/14/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
UG Cover Inspection. Troy N Phone #: ###-#### Inspection requested via web by Nathan Stenquist
|
INSP-Sprinkler Rough-in | 7/22/2019 | 7/22/2019 | 7/22/2019 | P | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping is complete, piping between conditioned spaces approved for cover, piping in attic spaces that requires tenting/freeze protection is not approved for cover until tenting is installed, inspected and approved.
Cameron Phone #: ###-####
|
Override - Parcel Holds | 7/22/2019 | 1/1/1900 | 7/22/2019 | | |
|
|
|
fire rough in
|
Issue and Print Permit | | | 4/29/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/23/2019 | | 4/26/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/26/2019 | | DONE |
|
|
|
met
|
Application received | | | 4/23/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 23 2019 7:40AM
|
Intake Approval | | | 4/23/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/23/2019 | | 4/23/2019 | | DONE |
Mark Stumbaugh
|
|
|
|