INSP-Final Inspection | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 3/24/2020 | 3/26/2020 | 3/26/2020 | P | FAIL |
Troy Cobbley
|
|
|
We finisher the inspection on elevator #2 but found that the power/control monitoring was not working and the sprinkler tamper switches are being reported as elevator smoke supervisory. All signals need to be reverified and the power monitoring repaired/tested.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
INSP-Final Inspection | 3/24/2020 | 3/24/2020 | 3/24/2020 | P | FAIL |
Troy Cobbley
|
|
|
Could not finish inspection due to the state elevator inspector tying up the second elevator. Will need to test this elevator and provide todays signal report.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Plan assigned to (Lee) | 3/19/2020 | | 3/20/2020 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/20/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 3/20/2020 | | 3/20/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/20/2020 | | DONE |
|
|
|
As built - No fee.
|
Permit Ready to Issue | | | 3/20/2020 | | DONE |
|
|
|
DO NOT ISSUE- as built
|
CHANGE STATUS TO (ISS) | | | 3/20/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/19/2020 | | DONE |
|
|
|
as built
|
INSP-Final Inspection | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | FAIL |
Troy Cobbley
|
|
|
Plan mods are need showing the actual means of communication. I noted missing Knox Box and unlabled dedicated circuit and a heat detector has been provided for elevator recall on exterior elevator door. No items tested or inspected.
Contact is Dirk. Phone #: ###-#### Inspection requested via web by Morgan Ahten
|
Issue and Print Permit | | | 5/21/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/21/2019 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 5/9/2019 | | 5/9/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 5/9/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 5/9/2019 | | 5/9/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/9/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/9/2019 | | DONE |
|
|
|
met
|
Application received | | | 5/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 8 2019 12:30PM
|