INSP-Final Inspection | 11/6/2019 | 11/7/2019 | 11/7/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Rick Fry Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
INSP-Sprinkler Rough-in | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in for the main piping re-route to the low ceiling area passed. As-builts are required prior to a final sign off. Piping can be covered. Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/20/2019 | 8/20/2019 | 8/20/2019 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where sprinkler piping is ok to cover.
Rudy Phone #: ###-####
|
Permit Ready to Issue | | | 6/14/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/14/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/13/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/13/2019 | | 6/13/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/13/2019 | | 6/13/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 5/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 29 2019 12:00PM
|
Intake Approval | | | 5/29/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Awaitng BLD permit to be issued.
|