INSP-Final Inspection | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Final Inspection | 7/19/2019 | 7/19/2019 | 7/19/2019 | A | CANC |
Troy Cobbley
|
|
|
Fire alarm permit has not been scheduled.
please call Adam with time frame. We would like to perform this in conjunction with the fire alarm test. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Can be finaled when interconnection with the fire alarm system has been tested. Adam Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 7/16/2019 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 7/12/2019 | | 7/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/15/2019 | | 7/15/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
Plan Mod Fee $150.00
|
Permit Ready to Issue | | | 7/15/2019 | | DONE |
|
|
|
plan mod so please do not re issue
|
Plan Modification Accepted | | | 7/12/2019 | | DONE |
|
|
|
changing sprinkler heads
|
Permit Ready to Issue | | | 6/6/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/6/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/5/2019 | | 6/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/5/2019 | | 6/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 6/4/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 4 2019 1:44PM
|