INSP-Final Inspection | 11/22/2019 | 11/25/2019 | 11/25/2019 | A | CANC |
Jim Page
|
|
|
Permit has been finaled in 22NOV2019.
UG inspections are complete. Flush completed on overhead permit. Please call Jeff with questions.
Thanks Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Final Inspection | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | PASS |
Jim Page
|
|
|
Final underground supply inspection is complete.
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for underground supply witnessed, no pressure loss observed.
underground Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining undergorund complete, approved for cover.
The rest of the underground cover Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for underground supply stub-up and first change of direction from under the footing complete, area inspected approved for cover, remaining underground to be inspected at a later date.
underground Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
Issue and Print Permit | | | 6/11/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/5/2019 | | 6/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/7/2019 | | DONE |
|
|
|
|
Application received | | | 6/5/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 5 2019 7:38AM
|
Intake Approval | | | 6/5/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/5/2019 | | 6/5/2019 | | DONE |
Mark Stumbaugh
|
|
|
|