INSP-Final Inspection | 7/5/2019 | 7/5/2019 | 7/5/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Charles Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/13/2019 | 6/13/2019 | 6/13/2019 | P | PASS |
Troy Cobbley
|
|
|
Insulation has been removed from blocking the upright sprinkler heads. Piping can be covered.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | FAIL |
Jim Page
|
|
|
Rough in inspection for new sprinkler piping complete, cover is not approved due to insulation/insulation foil is resting on some of the uprights, insualtion and foil must be secure and not resting/blocking fire sprinkler heads.
Jon Beazer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Application received | | | 6/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 7 2019 3:56PM
|
Intake Approval | | | 6/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/7/2019 | | 6/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/7/2019 | | 6/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/7/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/7/2019 | | DONE |
|
|
|
|