INSP-Final Inspection | 8/5/2019 | 8/5/2019 | 8/5/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Please call Adam for inspection. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 7/9/2019 | 7/10/2019 | 7/10/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover.
Adam Phone #: ###-####
|
Issue and Print Permit | | | 6/11/2019 | | DONE |
|
|
|
|
Application received | | | 6/10/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 10 2019 9:41AM
|
Intake Approval | | | 6/10/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/10/2019 | | 6/10/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/10/2019 | | 6/10/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/10/2019 | | DONE |
|
|
|
|