INSP-Final Inspection | 2/5/2020 | 2/6/2020 | 2/6/2020 | A | PASS |
Jim Page
|
|
|
Previously noted items have been c orrected, final fire sprinkler inspection is complete.
we have a scissor lift on site to be able to verify the placement of the heads at at 38 feet. Phone #: ###-#### Inspection requested via web by Connie Danes
|
INSP-Final Inspection | 12/12/2019 | 12/16/2019 | 12/16/2019 | A | FAIL |
Jim Page
|
|
|
Numerous heads blocked by drain piping when heads were changed to pendants. HVAC diffuser appears to be over 48 inches, did not have a lift to verify sizing of diffuser, possible addition of heads based on sizing.
Ken Danes Phone #: ###-#### Inspection requested via web by Connie Danes
|
Issue and Print Permit | | | 6/20/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/18/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/18/2019 | | 6/18/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/18/2019 | | 6/18/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Drawings
Small documents only.
|
Permit Ready to Issue | | | 6/18/2019 | | DONE |
|
|
|
met
|
Application received | | | 6/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 17 2019 2:16PM
|