CHANGE STATUS TO (ISS) | | | 9/5/2019 | | DONE |
|
|
|
per troy only partial pass
|
INSP-Final Inspection | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PART |
Troy Cobbley
|
|
|
A temporary for this permit is being given until an upgrade agreement has been finalized with the Boise Fire Dept for the fire alarm system.
This inspection needs to be before 7:30 am as this is a school and they will be in session. Please call ahead to Brian @ ###-####. Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
INSP-Final Inspection | 8/29/2019 | 8/30/2019 | 8/30/2019 | A | FAIL |
Troy Cobbley
|
|
|
FIre smoke damper did not function when smoke detector activated. Both dampers will need to be tested. Per Boise Fire a temp for fire alarm will be ok, when dampers function, until the fire alarm upgrade agreement is finalized. Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
Plan resubmittals received | | | 8/19/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 8/19/2019 | | 8/19/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/19/2019 | | DONE |
|
|
|
As built - No fee.
|
Permit Ready to Issue | | | 8/19/2019 | | DONE |
|
|
|
per Lee M no as built fee
|
CHANGE STATUS TO (ISS) | | | 8/19/2019 | | DONE |
|
|
|
per Lee M no as built fee
|
INSP-Final Inspection | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | FAIL |
Mark Scharfen
|
|
|
CO/Supervisory monitoring is not tied into AES, has not been pretested. Had conversation with technician. Will need to be scheduled after system has been properrly pretested.
end of day inspection if possible. please call ahead to coordinate. Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
Plan resubmittals received | | | 8/16/2019 | | DONE |
|
|
|
request to open for as built by Kristen from Johnson Control
|
Plan assigned to (Lee) | 8/16/2019 | | 8/16/2019 | | DONE |
Lee G Meredith
|
|
|
as built
|
1st review completed | | | 8/16/2019 | | FAIL |
|
|
|
Previously noted item that required correction has not been addressed. CO alarm is to report to the monitoring station as an alarm. It still shows as a supervisory on the drawings.
|
INSP-Final Inspection | 8/12/2019 | 8/14/2019 | 8/14/2019 | P | CANC |
Mark Scharfen
|
|
|
Last call of the day if possible. Phone #: ###-#### >> Inspection requested via web by Kristin Dolan Inspection cancelled from web by: Kristin Dolan
|
Issue and Print Permit | | | 6/27/2019 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 6/19/2019 | | 6/20/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 6/20/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 6/20/2019 | | 6/20/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/20/2019 | | DONE |
|
|
|
Passed with commnets.
|
Permit Ready to Issue | | | 6/20/2019 | | DONE |
|
|
|
met
|
Application received | | | 6/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2019 12:34PM
|