INSP-Final Inspection | 3/25/2020 | 3/25/2020 | 3/25/2020 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Final Inspection | 3/24/2020 | 3/24/2020 | 3/24/2020 | P | FAIL |
Troy Cobbley
|
|
|
Need overhead and underground test papers.
RICK FRY IS OUR CONTACT Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Troy Cobbley
|
|
|
24 air test passed.
rick is contact this is to complete our 24 hour air test Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | DONE |
Troy Cobbley
|
|
|
Started 24 hour air test at 9:00am with 65 psi on the guage.
RICK FRY IS OUR CONTACT. THIS WIL BE A 24 HOUR AIR TEST ON THE DRY SYSTEM Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2020 | 2/28/2020 | 2/28/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping on levels 1 and 2 witnessed, no pressure loss observed.
ROY IS OUR FOREMAN Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2020 | 1/23/2020 | 1/23/2020 | A | PASS |
Troy Cobbley
|
|
|
2nd floor rough in pass. Verify baffles are installed on 2nd floor.
RUDY IS OUR CONTACT. THIS IS A ROUGH-IN FOR THE 2ND FLOOR Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
INSP-Sprinkler Rough-in/Hydro | 1/20/2020 | 1/21/2020 | 1/21/2020 | A | PASS |
Troy Cobbley
|
|
|
First floor rough in passed.
RUDY IS OUR CONTACT. THIS IS A ROUGH-IN FOR THE 1ST FLOOR ONLY AT THIS TIME Phone #: ###-#### Inspection requested via web by Brad Bettencourt
|
Plan resubmittals received | | | 7/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/3/2019 | | 7/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 7/3/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/3/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/3/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/3/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/24/2019 | | 6/25/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 6/24/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/24/2019 | | 6/24/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 6/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 21 2019 6:37AM
|