INSP-Final Inspection | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler ispection for area of work complete.
Darius Phone #: ###-####
|
INSP-Final Inspection | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | CANC |
Troy Cobbley
|
|
|
Not ready for final yet.
Darius Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | FAIL |
Troy Cobbley
|
|
|
Sprigs exceed 4' so they need bracing.
|
Plan resubmittals received | | | 8/2/2019 | | DONE |
|
|
|
per nathan, add few more sprinkler heads
|
Plan assigned to (Stumbaugh) | 8/2/2019 | | 8/2/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 8/2/2019 | | 8/2/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Fee
|
Permit Ready to Issue | | | 8/2/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/16/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/16/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 7/16/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/15/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/15/2019 | | 7/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/15/2019 | | 7/15/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 6/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 21 2019 1:34PM
|
Intake Approval | | | 6/21/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|