INSP-Final Inspection | 9/9/2019 | 9/10/2019 | 9/11/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
All of the bent piping appears to meet NFPA 13 6.3.8. Contact: Steven Vaughn Phone #: ###-#### Inspection requested via web by Hunter Fillmore
|
INSP-Sprinkler Rough-in | 9/9/2019 | 9/10/2019 | 9/10/2019 | A | PART |
Troy Cobbley
|
|
|
The deflector distance from the ceiling has been corrected but the hydro test failed due to visible leakage. Contact: Steven Vaughn Phone #: ###-#### Inspection requested via web by Hunter Fillmore
|
INSP-Sprinkler Rough-in | 9/6/2019 | 9/9/2019 | 9/9/2019 | A | FAIL |
Troy Cobbley
|
|
|
Corrections have been made except for the minimum destance from the sidewall deflector to the ceiling. Contact: Steven Vaughn Phone #: ###-#### Inspection requested via web by Hunter Fillmore
|
Plan assigned to (Stumbaugh) | 9/3/2019 | | 9/4/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 9/4/2019 | | 9/4/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 9/4/2019 | | DONE |
|
|
|
Plan Mod Approved
|
CHANGE STATUS TO (ISS) | | | 9/4/2019 | | DONE |
|
|
|
plan mod
|
Plan Modification Accepted | | | 9/3/2019 | | DONE |
|
|
|
Per Hunter, plan modification for 2 heads have been added
3 heads have been changed from sidewall to pendant configuration
walls have been changed to reflect renovations
piping has been rerouted to reflect field conditions.
The riser has been moved a few feet along the wall it was previously mounted on.
The system has been recalculated to reflect these changes.
|
INSP-Sprinkler Rough-in | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | FAIL |
Troy Cobbley
|
|
|
As-builts or plan mods are needed showing the piping routing changes (additional fittings), per the data sheet for the sidewall heads the min. mounting distance from the ceiling 4" but the heads have been installed at 3 1/2". Also the sidewall heads have a max distance to be mounted off a wall and that has been exceeded. Verification needs to be provided that shows the heads have been installed per their listing. I noted the center line in the garage has no wall behind the sidewall heads again is this listed. I will need verification from the state that sprinkler coverage is not needed in the closet close to the riser. I will need to see the tenting where the piping passes above the Kitchen cabinets. I have not looked at any of the fire pump/tank items. Contact: Ricky Sullivan Phone #: ###-#### Inspection requested via web by Hunter Fillmore
|
Sprinkler Plan Check | 6/27/2019 | | 6/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/28/2019 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/28/2019 | | DONE |
|
|
|
|
Application received | | | 6/27/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 27 2019 3:09PM
|
Intake Approval | | | 6/27/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/27/2019 | | 6/27/2019 | | DONE |
Mark Stumbaugh
|
|
|
|