INSP-Final Inspection | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for undergorund supply has been witnessed, no pressure loss observed.
|
INSP-Final Inspection | 9/5/2019 | 9/5/2019 | 9/5/2019 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in | 8/20/2019 | 8/21/2019 | 8/21/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
Troy Nelson will call for inspection when he is close to finished. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
Issue and Print Permit | | | 7/1/2019 | | DONE |
|
|
|
|
Application received | | | 6/28/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 28 2019 2:17PM
|
Intake Approval | | | 6/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 6/28/2019 | | 6/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 6/28/2019 | | 6/28/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 6/28/2019 | | DONE |
|
|
|
met
|