INSP-Final Inspection | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Contact Noemi Carrero ###-#### 30 min prior to Fire Final Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 7/25/2019 | 7/26/2019 | 7/26/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, area of work approved for cover.
Contact Noemi Carrero ###-#### 30 min prior to RTC insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
Issue and Print Permit | | | 7/22/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/18/2019 | | 7/19/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 7/19/2019 | | DONE |
|
|
|
met
|
Intake Approval | | | 7/18/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/18/2019 | | 7/18/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 7/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 17 2019 10:24AM
|