INSP-Final Inspection | 9/30/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Jeff Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
|
Application received | | | 7/31/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 31 2019 9:26AM
|
Intake Approval | | | 7/31/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 7/31/2019 | | 7/31/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 7/31/2019 | | 7/31/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/2019 | | DONE |
Mark Stumbaugh
|
|
|
No associated BLD permit.
|
Permit Ready to Issue | | | 7/31/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 7/31/2019 | | DONE |
|
|
|
|