INSP-Final Inspection | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final Inspection | 10/7/2019 | 10/10/2019 | 10/10/2019 | A | CANC |
Jim Page
|
|
|
Core and shell permits need to be finaled before TI final, this final needs to be coordinated with the fire alarm contractor to finish fire sprinkler alarm related devides, this request is cancelled per conversation with Rick Fry.
Adam Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/7/2019 | 10/10/2019 | 10/10/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining overhead fire sprinkler piping is complete, approved for cover.
Adam Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/27/2019 | 8/28/2019 | 8/28/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fir esprinkler piping above hardlids complete, approved for cover.
Kerry Phone #: ###-####
|
Issue and Print Permit | | | 8/5/2019 | | DONE |
|
|
|
|
Application received | | | 8/2/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 2 2019 1:44PM
|
Intake Approval | | | 8/2/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 8/2/2019 | | 8/2/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 8/2/2019 | | 8/2/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 8/2/2019 | | DONE |
|
|
|
|