INSP-Final Inspection | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for scope of work complete.
Adam Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler scope of work complete.
Adam Phone #: ###-####
|
Issue and Print Permit | | | 8/8/2019 | | DONE |
|
|
|
|
Application received | | | 8/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 7 2019 2:41PM
|
Intake Approval | | | 8/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 8/7/2019 | | 8/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 8/7/2019 | | 8/7/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 8/7/2019 | | DONE |
|
|
|
|