INSP-Final Inspection | 1/21/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Jim Page
|
|
|
As-builts have been submitted and approved. Final fire sprinkler inspection complete.
Please contact Rick Fry for inspection time. Phone #: ###-####
|
Plan assigned to (Stumbaugh) | 1/21/2020 | | 1/22/2020 | | DONE |
Mark Stumbaugh
|
|
|
as build per Dan from TVFP- to show ceiling grid
|
Sprinkler Plan Check | 1/22/2020 | | 1/22/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/22/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1 hr
Minus 17 devices
|
Permit Ready to Issue | | | 1/22/2020 | | DONE |
|
|
|
plan mod met
|
CHANGE STATUS TO (ISS) | | | 1/22/2020 | | DONE |
|
|
|
|
INSP-Final Inspection | 1/20/2020 | 1/21/2020 | 1/21/2020 | P | CANC |
Jim Page
|
|
|
Fire alarm inspection is scheduled for 22JAN2020, this inspection will need to be rescheduled to coincide with final fire alarm inspection, this request is cancelled.
Please contact Rick Fry for inspection time. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
Plan resubmittals received | | | 1/21/2020 | | DONE |
|
|
|
as build per Dan from TVFP- to show ceiling grid
|
INSP-Sprinkler Rough-in/Hydro | 1/15/2020 | 1/16/2020 | 1/16/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided guage.
Please contact Troy Nelson for an inspection time. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in | 1/16/2020 | 1/16/2020 | 1/16/2020 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete. Notated city approved plans with red ink areas approved for cover. South side tenant spaces show grided ceiling being installed, grid to be installed with future tenants. City approved plans need to reflect deletion of pendant heads.
|
INSP-Sprinkler Rough-in | 11/13/2019 | 11/13/2019 | 11/13/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids complete, hardlids approved for cover.
Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans or small documents on site. I noted there will be an issue with the FDC placement in relation to the wall post indicator.
Please contact Cameron for inspection time for this afternoon. Call for a morning time inspection if possible. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
INSP-Sprinkler Rough-in/Hydro | 8/26/2019 | 8/26/2019 | 8/26/2019 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro witnessed.
Troy will call when ready for inspection. This inspection is for an underground service Hydro-test. Phone #: ###-#### Inspection requested via web by Daniel Buccino
|
Issue and Print Permit | | | 8/16/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/16/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/13/2019 | | 8/15/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 8/15/2019 | | |
|
|
|
|
Intake Approval | | | 8/13/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 8/13/2019 | | 8/13/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 8/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 8 2019 1:16PM
|