INSP-Final Inspection | 5/4/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete, no irrigation system was installed, zero scape type landscaping installed at time of inspection. Noted that if homeowner installs an irrigation system that operates off of the metered water then irrigation shutdown on flow swith activation is required.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2020 | 5/4/2020 | 5/4/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler pipe witnessed at city pressure, no pressure loss observed at riser provided gauge.
Hydro before final, call James before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 1/24/2020 | 1/24/2020 | 1/24/2020 | P | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed. Piping can be covered. Call Anthony when heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 1/12/2020 | 1/13/2020 | 1/13/2020 | A | FAIL |
Jim Page
|
|
|
Appears that no corrections to tenting have been made, reference notes entered on the 09JAN2020 inspection.
Tenting. Call James when heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 1/9/2020 | 1/9/2020 | 1/9/2020 | P | FAIL |
Jim Page
|
|
|
Tenting held up by gas piping, can lights, electrical wiring and areas where the sheeting is not installed correctly, pocket between sheetrock on piping will be compromised, no cover is approved, inspection stopped on level 1.
Tenting inspection, call James when heading out Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 11/25/2019 | 11/27/2019 | 11/27/2019 | A | PART |
Jim Page
|
|
|
Previously noted items have been corrected, rough in inspection complete, no tenting installed at time of inspection, cover is not approved until tenting is installed, inspected and approved.
Please call before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Permit Ready to Issue | | | 11/21/2019 | | DONE |
|
|
|
as built no fees
|
CHANGE STATUS TO (ISS) | | | 11/21/2019 | | DONE |
|
|
|
as built
|
Plan resubmittals received | | | 11/20/2019 | | DONE |
|
|
|
Nate from Thorpe Fire and Sprinkler called and requested to begin an as built workflow
|
Plan assigned to (Stumbaugh) | 11/20/2019 | | 11/20/2019 | | DONE |
Mark Stumbaugh
|
|
|
as built
|
Plan Modification Accepted | | | 11/20/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 11/20/2019 | | 11/20/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2019 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1hr
2 new devices
|
INSP-Sprinkler Rough-in | 11/19/2019 | 11/19/2019 | 11/19/2019 | A | FAIL |
Jim Page
|
|
|
Install on level 1 does not match city approved drawings, inspection was stopped half way through level 1.
Call before heading out, rough and tenting. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 8/30/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/30/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/26/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 8/26/2019 | | 8/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 8/26/2019 | | 8/26/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 8/26/2019 | | DONE |
|
|
|
|
Application received | | | 8/13/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 13 2019 11:36AM
|
Intake Approval | | | 8/13/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Awaiting BLD permit to be issued.
|