INSP-Final Inspection | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | PART |
Troy Cobbley
|
|
|
Work in phase 1 is complete. POC is Karl with Orchard Partners Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Final Inspection | 8/15/2019 | 8/15/2019 | 8/15/2019 | P | CANC |
Troy Cobbley
|
|
|
Not ready for final.
Nate is the Contact Phone #: ###-#### Inspection requested via web by Chris Green
|
INSP-Sprinkler Rough-in | 8/15/2019 | 8/15/2019 | 8/15/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
Nate is the Contact Phone #: ###-#### Inspection requested via web by Chris Green
|
Application received | | | 8/14/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 14 2019 7:49AM
|
Intake Approval | | | 8/14/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 8/14/2019 | | 8/14/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 8/14/2019 | | 8/14/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/14/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 8/14/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 8/14/2019 | | DONE |
|
|
|
|