INSP-Final Inspection | 8/30/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
Issue and Print Permit | | | 8/23/2019 | | DONE |
|
|
|
|
Intake Approval | | | 8/22/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 8/22/2019 | | 8/22/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 8/22/2019 | | 8/22/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 8/22/2019 | | DONE |
|
|
|
|
Application received | | | 8/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 20 2019 3:57PM
|