INSP-Final Inspection | 11/5/2019 | 11/5/2019 | 11/5/2019 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
Todd Ketterling is the field contact. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/4/2019 | 11/5/2019 | 11/5/2019 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
Todd Ketterling is the field contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/25/2019 | 9/26/2019 | 9/26/2019 | A | PASS |
Troy Cobbley
|
|
|
The piping to the two heads in the hard lids is ok for cover. Todd Phone #: ###-####
|
Override - Parcel Holds | 9/25/2019 | 1/1/1900 | 9/25/2019 | | |
|
|
|
Inspection is for fire not mechanical
|
Application received | | | 8/23/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 23 2019 7:53AM
|
Intake Approval | | | 8/23/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 8/23/2019 | | 8/23/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 8/23/2019 | | 8/23/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 8/23/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 8/23/2019 | | DONE |
|
|
|
|