INSP-Final Inspection | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | CANC |
Troy Cobbley
|
|
|
Per note on the plans the existing fire alarm system will need to meet current code. I spoke to the contractor about the issue. No inspection performed.
Phone #: 4087506433 >> Inspection requested via mobile web by Josiah
|
Plan assigned to (Lee) | 12/9/2019 | | 12/10/2019 | | DONE |
Lee G Meredith
|
|
|
Plan mod to replace existing fire alarm panel.
|
1st review completed | | | 12/10/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 12/10/2019 | | 12/10/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 12/10/2019 | | PASS |
|
|
|
Quick permit plan modification approved, as noted on the fire alarm pland drawing. Minimum review fee of $65.00 due.
FACP replacement requires entire system to be brought up to current code compliance.
|
Permit Ready to Issue | | | 12/10/2019 | | DONE |
|
|
|
plan mod
|
CHANGE STATUS TO (ISS) | | | 12/10/2019 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 12/9/2019 | | DONE |
|
|
|
start plan mod workflow per Dante Frassa at Apex Boise
|
INSP-Final Inspection | 12/4/2019 | 12/5/2019 | 12/5/2019 | A | FAIL |
Troy Cobbley
|
|
|
A plan modification is required showing the fire alarm panel that was installed previously without a permit.
Phone #: 2088990672 >> Inspection requested via mobile web by Josiah
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2019 | 12/5/2019 | 12/4/2019 | A | CANC |
Jim Page
|
|
|
Phone #: 2088990672 >> Inspection requested via mobile web by Josiah Inspection cancelled via mobile web on Wednesday, December 04, 2019.
|
INSP-Final Inspection | 11/15/2019 | 11/15/2019 | 11/15/2019 | P | FAIL |
Jim Page
|
|
|
Manufactures specs for fire panel requires the panel to be in an environment conditioned between 32 degrees fahrenheit to 120 degrees fahrenheit, provide conditioning in fire panel enclosure as discussed, conditioning has been provided for communicator encloser, heat detectors can remain in current location.
As early as possible Phone #: 2088990672 >> Inspection requested via mobile web by Josiah
|
Telephone call | | | 10/24/2019 | | DONE |
|
|
|
Josiah called to say that there are no spare zones to add the panel heat detector and wanted to know if the heat could be tied to a pull station zone. I informed him that if the pull stations are on floor by floor zones that he could put the heat on the same zone as the pull for that floor. Pull stations are currently the only alarm initiating devices so this should not create confusion.
|
INSP-Final Inspection | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | FAIL |
Troy Cobbley
|
|
|
No testing performed. Provide data that provide assurance that the new communicator will be maintained with-in the listed temperature range of 32 degrees to 120 degress. Also provide a smoke detector (heat may be ok) for the protection of the equipment as per NFPA 72. Drawing need to reflect the changes. Phone #: 2088990672 >> Inspection requested via mobile web by Josiah
|
Plan assigned to (Lee) | 9/3/2019 | | 9/3/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 9/3/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 9/3/2019 | | 9/3/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 9/3/2019 | | DONE |
|
|
|
Quick permit passed. No comments.
|
Override - Parcel Holds | | | 9/3/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 9/3/2019 | | DONE |
|
|
|
MET
|
Issue and Print Permit | | | 9/3/2019 | | |
|
|
|
|
Application received | | | 8/29/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 29 2019 8:25AM
|